Project Description
Titangeomining was awarded the contract to excavate four former CCR basins, two coal pile runoff ponds and an ash stack area so that the land can be redeveloped for a future power generation unit. The 90-acre project includes dewatering the existing basins, confirming clean closure by visual inspection and achieving closure grades and then backfilling all ponds to match surrounding grades. All materials excavated from the site were hauled to a private, third part municipal solid waste landfill.
Titangeomining removed 620,00 cubic yards of ash and impacted soil material and hauled them 25 miles to a MSW landfill operated by a private waste company. Once the ponds were cleaned, over 700,000 cubic yards of new soils were imported to backfill the excavated areas to match surrounding grades. The imported fill was compacted to 95% standard proctor to support future re-development of the former coal generating plant area with a new generating unit. Provisions for addressing buried asbestos throughout the site we in place throughout the project.
Scope Of Work
De-mucking of six existing CCR and Coal Pile Runoff ponds.
340,000 cy of material hauled to an offsite MSW landfill. Managing of all contact waters through the plant’s existing water treatment processes. Clean closure of the ponds to State specifications.